XCMG wholeheartedly serves to escort your success!
Since the beginning of the year, the asphalt station market has heated up rapidly. A brand-new 4000 integral asphalt station, bathed in the warm sun of spring, stands on the land of the motherland. The wind and snow baptism and the blockade of the epidemic situation have failed to stop its rise. Behind it is the figure of XCMG's service team.
In late February, XCMG 4000 integral asphalt station began construction, and soon encountered continuous heavy snow. The highest temperature during the day was only minus 7 ℃ and even dropped to minus 10 ℃ at night. The service engineers for outdoor construction, wearing thick gloves and hats, were fully armed and worked hard to rush for time and catch up with the progress. However, the power and water cut off caused by transformer failure made the installation work in trouble.
"Rush to repair! The current construction progress has fallen behind. We must find ways to overcome difficulties and ensure the timely delivery of products!" The service staff refused to delay for a moment and went up to the difficulties, showing the courage and responsibility of worker Xu.
The service staff said proudly: "at that time, we still used such a simple tool as manual hoist to rush the construction period. In the face of so many difficulties, we still completed all the installation of the main body of the integrated asphalt station in 22 days. I think this is the" wholehearted "service spirit we have always guaranteed to our customers, overcome all difficulties and complete our commitment to our customers!"